D-2 CSE Capacity Calculation project entered in the external dry run

06 August 2015

As Regional Security Coordination Initiatives (RSCIs) Coreso and TSCnet are actively participating in the CSE Capacity Calculation project: two days-ahead, daily calculating the maximum import Net Transfer Capacities at the northern Italian border.

On 30th July, the project successfully moved into the external dry run, with daily publication of the process results on CASC web site for the first delivery day on 1st August.

The aim is to provide to market participants the opportunity to acquire sensitivity and experience about this new process.

Next step will be, after the completion of the external dry run, to enter into the full live test: with the aim of giving that new daily computed NTCs to the market players. This phase is expected to start on November 2015.

> CASC project website

> CASC values website