CWE entire D2CF model

11 September 2016

Since October 11th, a CWE single data merge for capacity calculation of Day Ahead Market Coupling  is done by Coreso.

The go-live of the full CWE D2CF merging by Coreso was planned on  11/10/2016 for the business day of 13/10/2016. On the same day, Amprion stopped the so called “German Pre-Merge” of the individual German D2CF data sets. Now, CORESO integrates the individual data (D2CF files) from the German TSOs directly during the merge of the CWE D-2 Common Grid Model.

This change will, among others, improve the efficiency of the merging processes.

The flow based process was not affected by this change.

Furthermore, this enhancement allows JAO to publish the aggregated information out of the D2CF files (output of Coreso merging process) on TSO level, this means that aggregated information will therefore be available for the German TSOs as well.